Introduction

In 1995, NCR Corporation embarked on a critical environmental project to remediate and manage PCB (polychlorinated biphenyls) contamination at its Oiso Factory site in Kanagawa Prefecture, Japan. This case study explores the strategies, challenges, solutions, and results of this large-scale environmental cleanup, led by the Regional Portfolio Director/Austvent Limited.

Challenge

The Oiso Factory site faced significant environmental and health risks due to PCB contamination. Key challenges included:

  • High Contamination Levels: The site and neighboring stream/river had substantial PCB contamination, posing risks to humans and wildlife.
  • Regulatory Compliance: Ensuring that all remediation activities complied with stringent local environmental regulations.
  • Cost Management: Managing the project within a budget of USD 25 million while achieving effective remediation.
  • Method Selection: Evaluating and selecting appropriate remediation methods based on effectiveness and cost-efficiency.

Solution

To address these challenges, a comprehensive remediation strategy was developed, focusing on containment and advanced treatment methods:

Containment Strategy

  • Entombment: Large concrete coffins were constructed on-site to contain the contaminated soil. This method was selected to prevent further environmental contamination and allow time for additional research into more permanent remediation techniques.
  • Annual Monitoring: Regular testing of groundwater and nearby soils was implemented to ensure the integrity of the containment structures. This monitoring ensured early detection of any potential leaks or damages.

Advanced Treatment

  • Pyrolysis: This method was analyzed for its effectiveness in breaking down PCBs at high temperatures. While not immediately implemented, it remained a potential future solution as research continued.
  • Research and Development: Ongoing research into new remediation technologies was supported to identify long-term solutions for complete PCB removal from the soil.

Regulatory Compliance and Stakeholder Engagement

  • Local Authority Approval: All remediation plans and results were submitted for approval by local environmental authorities, ensuring regulatory compliance.
  • Stakeholder Communication: Transparent communication with local stakeholders, including the community and environmental groups, was maintained to build trust and ensure project support.

Results

The environmental cleanup project at the Oiso Factory site achieved several critical outcomes:

  • Successful Containment: The construction of concrete coffins effectively contained the contaminated soil, preventing further environmental and health risks.
  • Regulatory Compliance: The project met all regulatory requirements, with plans and results approved by local authorities.
  • Cost Management: The project was completed within the allocated budget of USD 25 million.
  • Ongoing Monitoring: Annual tests confirmed the integrity of the containment structures, with no significant leaks or damages detected.

Conclusion

The PCB contamination remediation at NCR’s Oiso Factory site underscores the importance of strategic planning, innovative solutions, and stakeholder engagement in environmental projects. By combining effective containment methods with ongoing research and monitoring, the project not only mitigated immediate risks but also paved the way for future advancements in PCB remediation technologies. This case study highlights how environmental health and engineering practices can successfully address complex contamination issues, ensuring long-term safety and compliance.

Recent advances in PCB removal from historically contaminated environmental matrices.

Partner With Us for Impact

Shape your sustainable future and join us drive systemic change in sustainable finance. Explore your path to net zero by building a sustainable future that meets the needs of the present without compromising future generations

STAY IN THE LOOP

Subscribe to our free newsletter.

Don’t have an account yet? Get started with a 12-day free trial